Fact Sheets of the Week

Featured Company:

Home > Civil Tech. > FLOAT-IN DAM - "In the Wet" Construction Methods

FLOAT-IN DAM - "In the Wet" Construction Methods

The Need

"In-the-Wet" construction methods use off-site prefabrication combined with lift-in or float-in of large precast segments onto pre-installed foundations. The segments are locked onto the foundations by underbase grouting and infilling of the segments with tremie concrete. These methods have included the innovative use of large precast units, floating structures and cofferdams, large barge crane installation, and deep foundation structures. "In-the-Wet" method would offer significant advantages over the traditional fixed cofferdam method, including substantial cost savings, shorter construction duration, reduced environmental impact, and greater construction safety.

The Technology

Ben C. Gerwick, Inc. is teamed with Bergmann Associates of Rochester, New York, and D'Appolonia of Pittsburgh, Pennsylvania, to design a replacement for Dam 2 on the Monongahela River for the US Army Corps of Engineers. Braddock Dam, on the Monongahela River, has been designed to be built using float-in concrete shells, up to 333 ft. long, fabricated offsite, floated into place over pre-installed foundation caissons, set-down, grouted in-place, then infilled with concrete.

Dam landing pre-installed caissons

The new dam will be a 600-foot long structure with four gate bays. The "In-the-Wet" construction plan calls for breaking the dam into two segments of 333-foot and 265-foot. The segments will be constructed as closed bottom boxes in a two level casting basin. The bottom of the boxes will be recessed for the pre-installed foundation caissons. As each segment is completed, it will be launched by flooding the basin and towed to the site for final outfitting. It will then be positioned over the foundation caissons with a mooring system mounted on the segment. Each segment will then be ballasted down onto 6 landing caissons and leveled with flat jacks. The pile tops and underbase will be grouted, and 8-foot of tremie concrete will be placed in the segment. Each segment will then be dewatered and the remainder of the dam including tainter gates will be completed in the dry. This "In-the-Wet" technology is expected to save $5 - $15 mil and reduce the construction time by one year. The final plans and specifications were completed in October of 1998. Construction is scheduled to be completed in 2002.

Completed dam in operation & View of heavy lift crane moving precast element

The Benefits

This method offers several advantages over conventional "In-the-Dry" construction:

Status

Ben C. Gerwick, Inc. is taking the lead in designing of the precast dam segments and developing the construction methods and procedures for:

Gerwick has participated in numerous studies regarding the use of off-site prefabrication technology for inland waterways for the U.S. Army Corps of Engineers, including:

Barriers

Points of Contact

Refrences

  1. Ben C. Gerwick, Inc. http://www.gerwick.com
  2. U.S. Army Corps of Engineering, Pittsburgh District - Lower Mon Project Factsheet

Disclaimer Statement

Neither the Construction Industry Institute nor Purdue University in any way endorses this technology or represents that the information presented can be relied upon without further investigation.

Comments

Add Comment

This site is operated and maintained by the Division of Construction Engineering & Management, Purdue University as a not-for-profit service to the construction industry