Concrete and
Masonry
The placement and finishing of concrete involves
many different tasks that can be automated. Automation is
especially effective in the conveyance of concrete with such
technologies as programmable concrete pumps, automated
horizontal distributors, and conveyor systems. Once the
concrete is in place, a variety of technologies are available to
perform vibrating, leveling, screeding, and finishing
activities. Cleaning and cutting of concrete can also be done
using automated technologies.
Opportunities are available as well to automate
masonry construction. Mobile bricklaying and robotic masonry
block installation machines provide accurate and efficient
placement of masonry units that minimize common risks to worker
safety and health while maintaining production.
Example Automated
Technologies:
The following are examples of automated concrete
and masonry technologies that are currently available for use:
|
Technology |
Description |
|
Surf-Robo |
Remote controlled
concrete finisher |
|
Concrete Horizontal
Distributor |
Spreads concrete
horizontally for slab pours |
|
Concrete Surface
Treatment |
Applies treatments to
concrete surfaces |
|
Concrete Troweling |
Remote controlled
concrete troweler |
|
Mobile Bricklaying |
Automated laying of
bricks in walls |
|
Beam and Column
Reinforcing Cage Robot |
Fabricates rebar cages
for beams and columns |
|
Robotic Masonry
Installer |
Automated installation
of masonry blocks |
|
Robotic Shotcrete |
Automated application of
shotcrete |
|
Robotized Spraying of
GFRC Panels |
Automated spraying of
GFRC panels |
|
Surface Preparation |
Prepares concrete
surfaces for treatment |
|
Water Absorbing Robot
for Concrete Surfaces |
Wicks excess water from
concrete surfaces |
|
HMC Handling |
Handles HMC without
human aid |
|
Rebar Bending |
Automated rebar bending
to desired specs |
|
Rebar Pre-assembly |
Pre-assembles rebar
prior to installation |
|
Robotic Reinforcing Bar
Fabricator |
Automated fabrication of
concrete reinforcing |
|
Heavy Rebar Placement |
Robotic arm for placing
heavy rebar |
|
Rebar Placement Crane |
Automated crane for
placing rebar |
|
Mobile Concrete
Distributor |
Programmable pump for
placing concrete |
|
Concrete Pouring Crane |
Automated placing of
concrete with a crane |
|
Automatic Concrete
Vibrator |
Automated concrete
vibrator |
|
CALM-Concrete Leveling |
Automated leveling of
concrete in forms |
|
Mobile Screeding |
Automated screeding of
concrete |
|
Tile Installation |
Automated installation
of tiles |
|
Precast Panel
Installation |
Automated installation
of precast concrete panels |
|
Panel Lifting |
Lifts and places precast
panels |
|
Concrete Wall Cleaning |
Automated cleaning of
concrete walls |
|
Jet Scraper |
Prepares concrete
surfaces by scraping |
|
Concrete Wall Cutting |
Automates the process of
cutting concrete walls |
|
Concrete Cutting |
Automates the process of
cutting concrete |
|
Abrasive Jet - Concrete
Cutting |
Cuts concrete using a
stream of particulates |
|
Concrete Block
Installation |
Automated installation
of concrete blocks |
Common Limiting
Design Features
The following are examples of design features
that often limit the use of automated concrete and masonry
technologies during construction:
-
Slope
changes on slabs and roadways.
-
Diagonal grade breaks.
-
Warped crowns.
-
Mid-slab protrusions and obstructions.
-
Non-uniform distribution of floor slab protrusions and
obstructions.
-
Inconsistent masonry block size, shape, and pattern.
-
Inconsistent reinforcing steel size and shape.
-
Varying surface textures and features.
-
A
lack of clearance for access and operation of the technology.
Recommended
Design Practices
The following are examples of suggested design
practices that facilitate the use of automated concrete and
masonry technologies during construction:
Concrete:
-
Provide tighter specifications for grade, slope, and
smoothness.
-
Maintain long continuous paving with constant slope.
-
Eliminate diagonal grade breaks, warped crowns, and
perpendicular curvature.
-
Eliminate mid-slab protrusions and obstructions.
-
Keep
utilities that penetrate concrete floor slabs grouped
together; do not spread the utilities out. If slab
protrusions/obstructions cannot be grouped together, keep them
as far apart as possible to allow for passage of equipment
between them.
-
Keep
anchor bolts below the finish floor.
-
Set
concrete pours to be within machine widths.
-
Specify concrete mix designs that allow for finishing by
automated equipment.
-
Design concrete placement phases to account for the
capabilities and feasibility of concrete extruders.
Masonry:
Reinforcing steel:
-
Use
repetitive rebar sizes, shapes, and lengths throughout the
structure.
-
Standardize rebar location within each structural element.
-
Use
smaller bars for easy fabrication.
-
Use
lap splices instead of mechanical or welded splices.
-
Use
standards conducive to the local rebar manufacturing facility.
General design practices:
Expected Benefits
The following are examples of benefits that have
been realized from the use of automated concrete and masonry
technologies during construction:
-
Increased quality of the concrete finished surfaces.
-
Improved ability to meet tighter finish/flatness
specifications.
-
Shorter time required to place the concrete and masonry.
-
Shorter time required to finish the concrete surfaces.
-
Decreased exposure to worker safety and health hazards.
Example productivity improvements that have been
realized:
|
Automated
Technology |
When automated
technology is used |
Productivity when technology
not used |
|
Set-up and
breakdown |
Productivity |
|
Laser
Screed |
-- |
4,000 sf/hr |
1,250 sf/hr |
|
1 hr. |
100 cy/hr |
60 cy/hr |
|
Bidwell
(PCC paver) |
2 days |
35 cy/hr |
10 cy/hr |
|
AC
Paver |
5 min. |
80 tons/hr |
60 tons/hr |
|
Mobile
Screeding |
1-2 days |
70 cy/hr |
30 cy/hr |
Implementation
Example
Automated Technology: Concrete
Extruder
Project: Monterey Undercrossing and
Stevens-Otty Frontage Road, Clackamas, OR
The project
involved the construction of a freeway overpass. Nearly 3,000
feet of MSE retaining wall rails were constructed during the
two-year project duration, but not all of the railing was
extruded. The only railing that was extruded was railing
attached to wall “H”. Wall H is over 2,000 feet long and the
extruder contractor completed the wall in two days. Although
wall H contained the longest stretch of railing, there were
other opportunities to utilize an extruder. Railing extending
along another wall, wall “P”, and onto the bridge itself, was
less than 300 feet in length and took the bridge contractor over
three weeks to complete. The railing along wall P and the
bridge was not extruded, but could have been if designed
differently. The extruder contractor pointed out that the
railing on wall H had a vertical back and curved face, allowing
for optimal utilization of their extruder, while the wall P and
bridge railing did not
(Wall design details).
Also, there was a railing height difference along the length of
the railing where it extended from wall P and onto the bridge.
Although attached, the height transition added to the overall
cost of extruding. Since the wall P and bridge railing was
under 300 feet in length and required a change in shape
configuration, the extruder contractor could not competitively
compete against conventional construction methods. Also, the
railing on wall P and the bridge had two vertical faces, which
magnifies any inconsistency and adds to the cost of using an
extruder. The extruder contractor added that having at least
one curved face helps to reduce the visibility of
inconsistencies to the human eye.
|